- Water reticulation completed in late May
- Kerb and Channel, along with base pavements and asphalt works completed in early June
- Service trenching and electrical works to commence in mid-late June
- Concrete works to follow in early July
Both Stages 4 and 4A are forecast for completion in Q3 2025, with titles on track to be received at this time.